Permits and Paperworks for Roadwork

To carry out work in road or foot path a permit or Memorandum of Authorisation (MOA) is required. We apply for necessary permits and MOAs and communicate with councils and Vic-roads regarding them.

When you used Vic-roads owned road you need a MOA to continue the work. This includes major roads, highways, freeways, tollways and arterial roads. Vic-roads take minimum 15 working days to respond to the application.

Most of the councils require permits to work on their road reserves. Depend on the council it takes 5-10 working days to receive a permit.